Question

Difficulty: MediumWork Rate and Combined Work

A textile manufacturing plant uses two automated weaving looms, Loom PP and Loom QQ, to produce standardized fabric orders. Working alone at its constant rate, Loom PP can complete a full fabric order in 88 hours, while Loom QQ working alone at its constant rate can complete the same order in 1212 hours. Loom PP begins working on a full order alone. After 33 hours, Loom QQ joins Loom PP, and both looms work together at their respective constant rates until the order is completed. How many total hours does it take, from the moment Loom PP begins, to complete the entire fabric order?

  1. A
    33
  2. 66Answer
  3. C
    7.57.5
  4. D
    1010
  5. E
    15.515.5

Answer

66 hours
In the first 33 hours, Loom PP completes 3×18=383 \times \frac{1}{8} = \frac{3}{8} of the job, leaving 58\frac{5}{8} of the job remaining. When Loom QQ joins, their combined rate is 18+112=524\frac{1}{8} + \frac{1}{12} = \frac{5}{24} of the job per hour. The time needed to complete the remaining 58\frac{5}{8} of the job is 5/85/24=3\frac{5/8}{5/24} = 3 hours. Adding the initial 33 hours of solo work gives a total of 66 hours.

Step-by-Step Solution

1
Determine the individual hourly work rates of Loom PP and Loom QQ.
Rate of Loom P=18P = \frac{1}{8} order/hour; Rate of Loom Q=112Q = \frac{1}{12} order/hour.
Work rate is the reciprocal of the total time needed to complete one full unit of work.
2
Calculate the fraction of the order completed by Loom PP during its 33 hours of solo operation.
Work completed by Loom P=3×18=38P = 3 \times \frac{1}{8} = \frac{3}{8} of the order.
Work done equals rate multiplied by time spent working.
3
Find the remaining fraction of the order to be completed.
Remaining work = 138=581 - \frac{3}{8} = \frac{5}{8} of the order.
The total job represents 11 whole unit of work.
4
Calculate the combined work rate when both looms operate together.
Combined rate = 18+112=324+224=524\frac{1}{8} + \frac{1}{12} = \frac{3}{24} + \frac{2}{24} = \frac{5}{24} order/hour.
When entities work together, their individual rates add up.
5
Determine the time required for both looms together to finish the remaining work.
Time together = 5/85/24=58×245=3\frac{5/8}{5/24} = \frac{5}{8} \times \frac{24}{5} = 3 hours.
Time equals remaining work divided by the combined work rate.
6
Calculate the total time from start to finish.
Total time = 3 hours (solo)+3 hours (combined)=6 hours3 \text{ hours (solo)} + 3 \text{ hours (combined)} = 6 \text{ hours}.
The total elapsed time is the sum of the solo operating time and the combined operating time.

Key Concept

Work Rate and Combined Work
Estimated Time:2m 0s
Rate this question